The Ministry of Energy and Mineral Resources has issued Regulation
No. 26 of 2017 on the Mechanism for the Recovery of Investment Costs in the Upstream Oil-and-Gas Sector (“
Regulation 26/2017”), which sets out a number of mechanisms relating to the reimbursement of investment costs incurred by upstream oil-and-gas contractors (“
Contractor”) during the management of working areas for the duration of the cooperation-contract transition period by the government.
[1]
These mechanisms will apply during the cooperation-contract transition period, which the government may choose to extend (either through the use of the cost-recovery or gross-split schemes).
[2] Alternatively the government may choose to discontinue a given cooperation contract.
Investment Costs
As a general rule, a Contractor is obliged to maintain equitable production value throughout a given cooperation-contract period. In order to achieve this, the Contractor is required to make the necessary investment within its working area.
[3]
However, all such investments must first be approved by the government via the Special Task Force for Upstream Oil-and-Gas Business Activities (
Satuan Kerja Khusus Pelaksana Kegiatan Usaha Hulu Minyak dan Gas Bumi - ”
SKK Migas”). In order to obtain approval, Contractors must submit working and budget plans (for cost-recovery cooperation contracts) or working contracts (for gross-split production-sharing contracts) to SKK Migas.
[4]
Upon making the relevant investment in their working area, a Contractor will be entitled to recover their investment costs. This recovery will be undertaken by the government during the cooperation-contract period.
[5]
Cost Recovery in the Event of Cooperation-Contract Extensions
If a cooperation contract with a Contractor is extended by the government, then any incomplete recovery may be settled during the cooperation contract’s extension period. Such extensions may either take the form of cost-recovery cooperation contracts or gross-split product-sharing contracts (“
PSC”). If the former applies, then the reimbursed investment costs will be classified as operational costs and will be recovered.
[6] However, if the latter applies, then the relevant investment costs will count as the Contractor’s PSC take.
[7]
Note that if a cooperation contract is extended through the use of a gross-split scheme and the government appoints another Contractor to jointly manage the working area with the existing Contractor, then the new Contractor will also be responsible for covering the investment-cost recovery. The recovery value covered by any new Contractor will be calculated proportionally according to the amount of its participating interest in the relevant working area.
[8]
Cost Recovery in the Event of the Discontinuation of Cooperation Contracts
If the government decides not to extend a cooperation contract with the existing Contractor but is not yet ready to appoint new Contractor, then the Ministry of Energy and Mineral Resources (“
Ministry”) may issue a set of specific procedures relating to the recovery of the relevant investment costs.
[9] However, if the government has already appointed a new Contractor, then any such recovery will be undertaken by the newly appointed Contractor.
[10]
The recovery value that needs to be paid by a new Contractor should cover the remaining amount of any investment costs which have not yet been recovered, or other value, as determined by the Ministry (upon the Ministry receiving a recommendation from SKK Migas). This amount must then be verified by SKK Migas and set out in a decision letter which should be sent to the management responsible for the working area in question (
surat penetapan pengelolaan wilayah kerja). The amount should also be included in the new cooperation contract.
[11]
Subsequently, both the new and the existing Contractors should enter into an agreement covering the relevant recovery procedure.
[12] Note that any recovery that is undertaken by a new Contractor will be categorized as said Contractor’s take and will not affect the profit-sharing calculation stipulated under the PSC.
[13]
Any cooperation contract which was signed prior to the issuance of Regulation 26/2017 must be adjusted so as take the abovementioned provisions into account.
[14]
Regulation 26/2017 has been in force since 30 March 2017.
RFS
......