Governor of Jakarta Regulation No. 195 of 2010 on the Implementation Guide for the Installation of Utility Networks (‘Regulation’) has been issued to govern the installation of utility networks, both underground and aboveground, in all locations in the greater Jakarta area (Special Capital Territory (DKI) of Jakarta).
Article 3 requires utility network owners to submit an annual plan to the Head of the Public Works Agency no later than the November of the preceding year.
For specific installation works, Articles 4 and 5 set out technical requirements for underground utility network installation. And Article 7 sets out complementary building requirements for underground and aboveground construction works.
Licenses, as issued by the Head of the Public Works Agency, are required under Article 11 for: utility network installations, repairs, complementary buildings, and emergency repair works. The licensing application procedures are set out in Articles 12, 13, 14, and 15. A review process is set out in Article 16, and involves administrative checks, a coordination meeting, a field inspection, and a levy calculation. A license will then be issued in accordance with Articles 17, 18, 19, and 20, respectively, if the application requirements are met and the necessary levies, as set out in Articles 30 through 32, are paid.
Expiration of licenses occurs on the specified date, with a possibility of extension available under Article 21, via an application setting out the reasons for the delay, to the Head of the Public Works Agency, that has to be made at least 7 days prior to the expiry date. Only a single extension is possible, and a new license has to be applied for if the installation works are not completed within the extension period. If the implementation of the utility network installation is not in accordance with the licence terms or has not commenced within 30 days of the licence being issued, the license can be revoked pursuant to Article 22.
Contractors are obliged to conduct certain preliminary activities, as enumerated by Article 23, such as reporting to the local city/district administrative office at least 3 days prior to commencing the work. The work itself is subject to the obligations set out in Articles 24 through 29, such as announcing any changes in the volume of work, restricting any open-pit works to 72 hours, and performing any maintenance work within the 6 month period after the initial handover, in Articles 27 (1), (2), and 29 (1), respectively.
In the event that a utility network has to be relocated due to works being carried out by the local government, Article 33 (1) states that the Governor can order the affected utility network owner/contractor to carry out any such relocation.
Sanctions are set out in Articles 35 through 37, and include written notices, suspension of activities, and the revocation of business licenses.
The Regulation repeals and replaces Governor of Jakarta Decision No. 149 of 2000 on the Implementation Guide for the Installation of Utility Networks Under and Above Ground in the Special Capital Territory of Jakarta.
For a discussion of Governor of Jakarta Regulation No. 128 of 2010 on the Installation of Utility Networks in Strategic Locations see ILD No. 185 10 December 2010.
The Regulation has been in force since 23 November 2010.
......