Governor of DKI Jakarta has recently issued Regulation No. 128 of 2010 on the Installation of Utility Networks in Strategic Locations (‘Regulation’). The Regulation is intended to optimize the spatial utilization in relation to the placement of utility networks (systems in the form of pipes and/or cables) in strategic locations. The Regulation aims to simplify the license procedures and improve public services.
Article 6 defines strategic locations as those stipulated by the Public Works Agency (in coordination with the Regional Works Unit (SKPD/UKPD)), which are prioritized for utility network placement. Such locations are those that run parallel to and intersect national roads, highways, artery roads, collector roads, green zones, pedestrian and certain other roads, as stipulated by the Public Works Agency. To install an underground utility network in a strategic location, an applicant must obtain a license from the Public Works Agency of DKI Jakarta. Article 5 (2) provides details of the application and the supporting documents that have to be submitted to the Head of the Public Works Agency, these include, among others:
|
-
|
Blueprints of the utility network placement plan;
|
|
-
|
Installation work schedule;
|
|
-
|
Limit or notation on length, diameter and the number of channels; and
|
|
-
|
A copy of the terms of references (TOR) for replacement works and/or the existing utility network placing.
|
Following the submission of the application, the Public Works Agency will review the administrative documents, conduct a site visit (together with the applicant and the SKPD/UKPD), and calculate and set the levies for such installation works. The Agency will issue a license with a specified validity period, which can be extended in the event the installation works have not been completed. It should be noted that the license is subject to revocation in the event that the installation works have not been started within 30 days of the issuance of the license.
Prior to commencing the installation work, certain procedures have to be completed, for instance, certain reports have to be made, safety requirements have to be met, and the necessary equipment must be prepared, as well as the material and labor required for the installation works. Technical requirements are set out in Article 11.
Any violations are subject to administrative sanctions in the form of written notices and orders to cease installation works. Following an order to cease installation works, a prohibition on conducting further installation works can also be issued for a period of 1 year.
The Regulation repeals its predecessors, Governor Decisions No. 439 of 1991 and No. 615/1999.
The Regulation has been in force since 8 July 2010.
......