Essential Sectors
|
|
No
|
Business Sectors
|
Activities
|
Provisions
|
|
1.
|
Finance and banking
|
- Insurance
- Banking
- Pawnshops
- Futures exchange
- Pension funds
- Financing institutions,
which are oriented towards physical service with customers.
|
- Work from Office (“WFO”) at 75% staffing capacity in locations that offer public services; and
- WFO at 50% maximum staffing capacity for office administrative services that support operations
|
|
2.
|
Capital markets
|
Oriented towards customer service and good capital market operations
|
WFO at 75% staffing capacity |
|
3.
|
Information and communication technology
|
- Mobile operators
- Data centers
- Internet
- Media relating to the dissemination of information to the public
|
|
4.
|
Hospitality (non-COVID-19 quarantine handling)
|
- Maximum capacity of 50% and only visitors that fall into the green and yellow categories in the PeduliLindungi application may enter;
- Mandatory use of the PeduliLindungi application to screen all employees and visitors.
|
|
5.
|
Export-oriented industries and support, with the following requirements:
- Must have secured Industrial Activity Operational and Mobility Licenses (Izin Operasional dan Mobilitas Kegiatan Industri/IOMKI) and must comply with technical regulations set by the Ministry of Industry;
- Must show sample proofs of goods export notification (Pemberitahuan Ekspor Barang/PEB) documents used during the last 12 months or other documents showing export plans;
- Must use the PeduliLindungi application for entry and exit arrangements; and
- Employees must not eat at the same time.
|
- WFO at 75% staffing capacity per shift and only at manufacturing/production facilities; and
- WFO at 50% staffing capacity for office administrative services that support operations
|
|
Critical Sectors
|
|
No
|
Business Sectors
|
Provisions
|
|
1.
|
Healthcare
|
WFO at 100% staffing capacity without exceptions
|
|
2.
|
Security and order
|
|
3.
|
Disaster management
|
- WFO at 100% staffing capacity per shift and only at manufacturing/production/construction facilities/public services; and
- WFO at 50% staffing capacity for office administrative services that support operations
|
|
4.
|
Energy
|
|
5.
|
Logistics, post, transportation and distribution, particularly to meet the basic needs of the community
|
|
6.
|
Food and beverages and supports, including for livestock/pets
|
|
7.
|
Fertilizer and petrochemicals
|
|
8.
|
Cement and building materials
|
|
9.
|
Objects of vital national importance
|
|
10.
|
Nationally strategic projects
|
|
11.
|
Construction (public infrastructure including telecommunications and broadcasting infrastructure)
|
|
12.
|
Basic utilities (electricity, water and waste management)
|
|
13.
|
Construction activities involving public infrastructure and private construction
|
|
Sectors Which Are Not Classified as Either Essential or Critical Sectors
|
|
50% WFO for employees who have been vaccinated and who are required to use the PeduliLindungi application at entry and exit points.
|