In a bid to strengthen domestic industries which are engaged in the production of cellular phones, handheld devices and tablet computers (collectively referred to as
“Telecommunications Gadgets”), the Ministry of Industry (“
Ministry”) has issued Regulation
No. 29/M – IND/PER/7/2017 on the Provisions and Procedures Used to Calculate Domestic-Component Levels for Cellular Phones, Handheld Devices and Tablet Computers (“
Regulation 29/2017”).
[1]
Prior to the issuance of Regulation 29/2017, these matters were addressed under Ministry Regulation
No. 65/M – IND/PER/7/2016 (“
Regulation 65/2016”).
[2]
In essence, this new regulation stipulates guidelines for the calculation and assessment of compliance with the mandated domestic component levels for Telecommunications Gadgets (
Tingkat Komponen Dalam Negeri -
“TKDN”) and addresses the following matters:
|
1. |
TKDN calculations; |
|
2. |
Calculation procedures; |
|
3. |
Verification agency; and |
|
4. |
Supervision. |
Due to the broad scope of Regulation 29/2017, this edition of Indonesian Legal Brief confines its discussion to points (1) and (2) only.
TKDN Calculations
As a general rule, any calculations of TKDN levels for Telecommunications Gadgets should cover three main areas: manufacturing, development and applications.
[3] Each of these areas should account for a specific proportion of any calculations which are undertaken, specifically: 70% for manufacturing, 20% for development and 10% for applications.
[4]
Calculations of the abovementioned areas depend upon several variables which are used to calculate the required TKDN levels. These variables are specified in the table below:
|
Aspect |
Calculation |
Additional Remark(s) |
|
Variable |
Proportion |
|
Manufacturing[5] |
Materials, including:
|
1. |
Display module assembly; |
|
2. |
Frame and casing; |
|
3. |
Flexible connectors; |
|
4. |
Vibration motors; etc. |
|
95% |
TKDN levels for these various materials are further elaborated upon based on several conditions which are set out under Articles 6 and 7 of Regulation 29/2017.
Previously, Regulation 65/2016 did not elaborate upon any TKDN levels for these materials. |
Manpower used for the following purposes:
|
1. |
Assembly; |
|
2. |
Testing; and |
|
3. |
Packing. |
|
2% |
TKDN levels for manpower are further elaborated upon based on several conditions which are stated under Article 8 of Regulation 29/2017.
Previously, Regulation 65/2016 did not elaborate upon any TKDN levels for manpower. |
Production machines used for the following purposes:
|
1. |
Assembly; and |
|
2. |
Testing. |
|
3% |
TKDN levels for production machines are further elaborated upon based on several conditions which are stated under Article 9 of Regulation 29/2017.
Previously, Regulation 65/2016 did not elaborate upon any TKDN for production machines. |
|
Development[6] |
Licensing (or ownership of intellectual property rights), for software/hardware development kits or reference designs created by main chipset vendors for any Telecommunications Gadget products |
10% |
- |
Firmware, for:
|
1. |
The development of operating systems and user interfaces; |
|
2. |
Injecting, testing and debugging software. |
|
40% |
In regard to the development of operating systems, the maximum TKDN level is set at 50% of the total TKDN portion for firmware.
Previously, the maximum TKDN level for the development of operating systems was set at 100% of the total TKDN portion for firmware.[7] |
Industrial design, covering:
|
1. |
Product design; and |
|
2. |
Mechanical design. |
|
20% |
By way of comparison, Regulation 29/2017 no longer requires foreign workers to be assisted by a minimum of three domestic workers during the development of any application for TKDN assessment purposes.[8] |
Integrated-circuit layout design, covering:
|
1. |
Creation of schematic diagrams and circuit-board layouts; |
|
2. |
Testing and calibration of printed-circuit-board assemblies (“PCBA”) and jig testing. |
|
30% |
Previously, Regulation 65/2016 required the testing and calibration of PCBA-Surface Mount Technology (PCBA-SMT) for TKDN assessment purposes, instead of general PCBA.[9] |
|
Applications[10] |
Component calculations, encompassing:
|
1. |
Design; |
|
2. |
Intellectual property; |
|
3. |
Manpower; |
|
4. |
Competence certification; and |
|
5. |
Work tools. |
|
As detailed under Articles 25-30 of Regulation 29/2017 |
Previously, Regulation 65/2016 required an application to only have 250,000 actives users for TKDN assessment purposes. However, Regulation 29/2017 now requires an application to have at least 500,000 active users.[11]
|
Various types of activity, covering:
|
1. |
App requirements; |
|
2. |
App designs; |
|
3. |
Programming; |
|
4. |
Testing; and |
|
5. |
Packaging. |
|
In addition, Regulation 29/2017 also specifies two other types of TKDN calculations, aside from the TKDN calculations which cover the abovementioned three aspects, specifically:
[12]
|
1. |
TKDN calculations for certain products, covering TKDN calculations for levels of manufacturing (10%), development (20%) and apps (70%);[13] and |
|
2. |
TKDN calculations based on innovative development. In this case, a TKDN calculation should be based on an investment value, as outlined in an innovative development proposal, as follows: 1) IDR 250 – 400 million (20%); 2) IDR 400 – 550 million (25%); 3) IDR 550 – 700 million (30%); 4) IDR 700 million – 1 billion (20%); or 5) more than IDR 1 billion (40%). |
By way of comparison, Regulation 65/2016 required any investment to be actualized at a level of at least 40% within a year of the relevant investment proposal being approved. However, this provision has no longer been incorporated under Regulation 29/2017.
[14]
Calculation Procedures
Compliance with the TKDN requirements are to be assessed by the relevant applicant upon request. The TKDN calculation procedure (with the exception of any TKDN calculations which are based on innovative development) is set out in the following flowchart:
[15]
The flowchart above assumes that the application being processed is complete and thus passes the described review process (as undertaken by the UP2 and the Director General). If a given application is deemed incomplete however, then the UP2 must inform the applicant in question or, at a later stage, the Director General must reject the assessment application.
[16]
Furthermore, Regulation 29/2017 also sets out new procedures for TKDN calculations which are based on innovative developments, as set out in the following flowchart:
[17]
Previously, Regulation 65/2016 did not distinguish between procedures for different types of TKDN calculations. However, Regulation 29/2017 now stipulates a new procedure for TKDN calculations which are based on innovative development.
[18]
Regulation 29/2017 has been in force since 14 July 2017 and repeals and replaces Regulation 65/2016.
AP2
[1]Recital (a), Regulation 29/2017. ......
Subscribe to read more legal analysis.
Hukumonline Pro Intelligence
Platform AI hukum terpercaya sebagai solusi komprehensif riset Anda
*Syarat dan ketentuan berlaku