Indonesian Nuclear Energy Legal Framework

Overview

As of 2011 the International Atomic Energy Agency (IAEA) records show that there are 436 Nuclear Power Plants located in 30 countries, and it is expected that a further 15 to 30 nuclear power plants will be constructed before 2030.

IAEA, as the international organization that is in charge of the supervision on the use of nuclear technology for non-proliferation purposes, has revealed that there are around 60 developing nations that have expressed their desire to use nuclear technology for energy generation purposes.

Indonesia is one of the countries that has expressed its intention to the IAEA, due to constraints in meeting the rising domestic demand for energy. In fact, power shortages have been a regular occurrence in the eastern part of Indonesia, especially on the island of Kalimantan (Borneo).

Indonesia has been preparing itself for the utilization of nuclear energy for a substantial amount of time, beginning with Law No. 31 of 1964 on General Provisions of Atomic Power, as later amended by Law No. 10 of 1997 on Nuclear Energy (“Nuclear Law”). However, until today, the development of nuclear power has not been realized, with the only developments being public discourse and the establishment of preparatory committees for nuclear power plants.

At present only nuclear research facilities exist in Indonesia, where the National Nuclear Agency (Badan Tenaga Nuklir / BATAN) is the leading national research agency on nuclear technology. BATAN has been in existence since 1985, having been established by Presidential Decree No. 82 of 1985 on the National Nuclear Agency. And has been followed by the establishment of the Nuclear Supervision Agency (Badan Pengawas Tenaga Nuklir / BAPETEN) by Presidential Decree No. 76 of 1998 on Nuclear Power Supervision Agency (“BAPETEN Decree”), which in essence functions to formulate national policy for supervising the use of nuclear technology.

This edition of the Indonesian Law Digest will highlight the key features of the legislative framework governing the construction and operation of a nuclear power plant and provide an analysis of the relevant provisions.

 

Purpose

Energy

Dispersed through the regions of Indonesia, energy supplied to consumers by the State Electricity Company (Perusahaan Listrik / PLN) derives from hydro power plants, geothermal power plants, and steam power plant that are fueled by fossil fuels, the price of which has seen substantial appreciation over the recent past.

In producing electricity, different power plant types have different abilities to increase or decrease the electricity output to fulfill the base load demand for energy. Although green alternative renewable energy sources such as wind power plants and solar power plants appear to be favored by the international community, they are unfortunately unable to provide an electricity supply of sufficient stability to cover the base load demand.

A number of countries derive a substantial portion of their electrical generation capacity from nuclear power plants, for instance: Lithuania at 76%, France at 75%, Slovakia at 53%, South Korea at 35%, Japan at 23%, and the United States at 20%.

Indonesia on the other hand, pursuant to Article 2 (6) of Presidential Decree No. 5 of 2006 on National Energy Policy, has stipulated that nuclear power, along with other new and renewable energy sources, has to supply at least 5% of the national energy needs. This policy was further supported by the issuance of Law No. 17 of 2007 on National Long Term Development for 2005-2025.

 

Nuclear Power Plants

As stipulated in Article 2 of the Government Regulation No. 43 of 2006 on Nuclear Reactor Licenses (“Nuclear License Regulation”), the development stages of nuclear power plants and reactors consist of three phases, respectively: erection of the nuclear reactor, operation of the reactor, and decommissioning.

The purpose of this ILD is to provide an overview of the legal framework involved in erecting a nuclear power plant through to the decommissioning phase.

 

Applicability

Pursuant to Article 13 (3) of the Nuclear Law in conjunction with Article 5 (3) of the Nuclear License Regulation, state owned enterprises, cooperatives, or private entities may erect, operate, and decommission nuclear reactors.

 

Foreign Ownership

As stated in Business Classification field (KBLI) number 35101 of Presidential Regulation No. 36 of 2010 on the List of Business Fields Closed to Investment and Business Fields Conditionally Open to Investment (“Negative Investment List”), foreign investors can own up to 95% of a nuclear power plant in Indonesia.

 

Licenses

Pursuant to Article 3 (d) of the BAPETEN Decree in conjunction with Article 6 of the Nuclear License Regulation, licenses for the use of nuclear technology are issued by BAPETEN. However, in relation to erecting a nuclear reactor, pursuant to Article 5 (4) of the Nuclear License Regulation, an applicant first has to secure a determination from the minister in charge of national energy security, whereby the minister has to consult with the House of Representative (Dewan Perwakilan Rakyat / DPR) before rendering its determination.

As set out in Article 6 (2) of the Nuclear License Regulation, an applicant has to secure 5 types of licenses, which are:

a.

Site License;

b.

Construction License;

c.

Commissioning License;

d.

Operating License; and

e.

Decommissioning License.

 

These licenses will be issued on a step-by-step basis by the Chairperson of BAPETEN, with the owner of the nuclear reactor having to secure all 5 licenses, pursuant to the elucidation of the Nuclear License Regulation preamble.

 

Administrative and Technical Requirements

Pursuant to Article 7 of the Nuclear License Regulation, to obtain the required licenses, the applicant has to fulfill the administrative and technical requirements. The administrative requirements include the formation of the legal entity and the compliance with the relevant regulations on legal entities and investment.

The technical requirements include such matters as: the quality assurance program, which consists of a safety system, grading system, documentation, management responsibility; and resource management, which consists of the implementation process, as well as the measurement, assessment and repair of the planned nuclear reactor.

Pursuant to Article 7 (5), the Chairperson of BAPETEN will issue a further regulation on the quality assurance program.

 

Site License

Pursuant to Article 9 of the Nuclear License Regulation, a site license applicant has to submit to the Chairperson of BAPETEN documents consisting of:

a.

The site evaluation report,

b.

Primary data on the planned nuclear reactor,

c.

List of information of the nuclear facility’s preliminary design, and

d.

Documentation on the quality assurance program.

 

Timeline

Pursuant to Article 10 (1) of the Nuclear License Regulation, upon submission of the documents required for a site license, the Chairperson of BAPETEN will have 1 month to issue a declaration on the completeness of the required documents.

Pursuant to Articles 10 (3) and (4) of the Nuclear License Regulation, an administrative and technical assessment will then commence, lasting at most 1 year, and will be followed by an issuance of a site license if the administrative and technical requirements are met (Article 10 (9)).

 

Construction License

A construction license has to be applied for within 4 years of a site license being issued (Article 12 (1) of the Nuclear License Regulation). The application requires the submission of the administrative documents listed in Article 7 (2) as well as the following:

a.

Preliminary safety analysis report,

b.

Detailed design of the nuclear reactor,

c.

Probabilistic safety analysis report on the commercial nuclear reactor,

d.

Construction program,

e.

List of information on the design,

f.

Preliminary Nuclear Safety System, describing the physical protection plan of the facility,

g.

Construction quality assurance program,

h.

An environmental feasibility decision from the appointed institution, and

i.

Evidence of financial capability, to ensure the implementation of construction.

 

Timeline

Pursuant to Article 13 (1) of the Nuclear License Regulation, upon submission of the documents required for a construction license, the Chairperson of BAPETEN will have 1 month to issue a declaration on the completeness of the required documents.

Pursuant to Articles 13 (3) and (4) of the Nuclear License Regulation, an administrative and technical assessment will then commence, lasting at most 2 years, and will be followed by an issuance of a construction license if the administrative and technical requirements are met (Article 13 (8)).

A construction license can be issued for at most 5 years (Article 14 (1) of the Nuclear License Regulation).

 

Commissioning License

Pursuant to Article 15 (1) of the Nuclear License Regulation, it is possible to apply for a commissioning license to the Chairperson of BAPETEN in the event that: the applicant has completed the construction phase; secured a license to utilize nuclear substances; and secured a reactor operator that holds a working license (such licenses being governed by Government Regulation No. 29 of 2008 on Licenses for the Use of Ionizing Radiation Sources and Nuclear Materials).

Pursuant to Article 15 (2), in addition to the administrative documents required by Article 7 (2), the following technical documents have to be submitted:

a.

Commissioning program,

b.

 Report on the construction process, including function test results on the structure, systems, and components of the nuclear reactor,

c.

Technical drawings of the nuclear reactor,

d.

Safeguard system and the Nuclear Safety System,

e.

Nuclear preparedness program,

f.

Commissioning quality assurance program,

g.

Environmental management and environmental monitoring reports,

h.

Evidence of financial capability, to ensure the accountability for any nuclear damage, and

i.

Evidence of financial capability, to guarantee decommissioning.

 

Timeline

Pursuant to Article 16 (1) of the Nuclear License Regulation, upon submission of the documents required for a commissioning license, the Chairperson of BAPETEN will have 1 month to issue a declaration on the completeness of the required documents.

Pursuant to Articles 16 (3) and (4) of the Nuclear License Regulation, an administrative and technical assessment will then commence, lasting at most 1 year, and will be followed by an issuance of a commissioning license if the administrative and technical requirements are met (Article 16 (8)).

A commissioning license can be issued for at most 2 years (Article 17 (1) of the Nuclear License Regulation), with implementation having to commence within 6 months of the license being issued.

 

Operating License

Pursuant to Article 18 (1) of the Nuclear License Regulation, it is possible to apply for an operating license to the Chairperson of BAPETEN in the event that: the applicant has completed the commissioning phase; secured a license to utilize nuclear substances; and secured a reactor operator that holds a working license (such licenses being governed by Government Regulation No. 29 of 2008 on Licenses for the Use of Ionizing Radiation Sources and Nuclear Materials).

Pursuant to Article 18 (2), in addition to the administrative documents required by Article 7 (2), the following technical documents have to be submitted:

a.

A final safety analysis report that includes the commissioning results, limitations and conditions of the nuclear facility’s operation, and the decommissioning program,

b.

Nuclear substance safeguard facility appendices,

c.

Report on the implementation of environmental management and environmental monitoring during commissioning,

d.

Operational quality assurance program,

e.

Evidence of financial capability to operate the nuclear facility.

 

Timeline

Pursuant to Article 19 (1) of the Nuclear License Regulation, upon submission of the documents required for an operating license, the Chairperson of BAPETEN will have 1 month to issue a declaration on the completeness of the required documents.

Pursuant to Articles 19 (3) and (4) of the Nuclear License Regulation, an administrative and technical assessment will then commence, lasting at most 2 years, and will be followed by an issuance of an operating license if the administrative and technical requirements are met (Article 19 (8)).

An operating license will be issued for at most 40 years (Article 20 (1) of the Nuclear License Regulation).

 

Operating License Extension

Since there are nuclear reactors designed to operate for more than 40 years, pursuant to Article 20 (2), at least 5 years prior to the expiry of the operating license, it is possible to request a license extension, which requires the submission of:

a.

Final safety analysis report,

b.

Operational activity report, and

c.

Aging research report.

 

Pursuant to Articles 20 (5) and (6), should the assessment by the Chairperson of BAPETEN find that the technical requirements have been fulfilled, the operating license will be extended for a further 20 years.

 

Decommissioning License

Nuclear reactor decommissioning is one of the obligations that a nuclear reactor owner is obliged to fulfill at the end of the lifecycle of a nuclear reactor. Pursuant to Article 24 (3) of the Nuclear License Regulation, at least 3 years prior to the expiry of the operating license an application for a decommissioning license has to be submitted to the Chairperson of BAPETEN.

Pursuant to Article 24 (2) of the Nuclear License Regulation, in addition to the administrative documents required by Article 7 (2), the following technical documents have to be submitted:

a.

Decommission program, and

b.

Decommission quality assurance program.

 

Timeline

Pursuant to Article 25 (1) of the Nuclear License Regulation, upon submission of the documents required for a decommissioning license, the Chairperson of BAPETEN will have 1 month to issue a declaration on the completeness of the required documents.

Pursuant to Articles 25 (3) and (4) of the Nuclear License Regulation, an administrative and technical assessment will then commence, lasting at most 1 year, and will be followed by an issuance of a decommissioning license if the administrative and technical requirements are met (Article 25 (8)).

A decommissioning license will remain valid until the issuance of the Exemption Statement by the Chairperson of BAPETEN (Article 26 of the Nuclear License Regulation).

 

Exemption Statement

To be relieved of the decommissioning obligation, pursuant to Article 28 (1) of the Nuclear License Regulation, a nuclear reactor owner has to secure an Exemption Statement from the Chairperson of BAPETEN. To obtain an Exemption Statement the owner has to submit:

a.

Report on the decommissioning of the nuclear reactor,

b.

Report on the treatment of the radioactive waste, and

c.

Report on environmental monitoring, including test results of radiation exposure and radioactive contamination inside and outside of the reactor site.

 

In treating radioactive waste it is necessary to comply with the provisions of Government Regulation No. 27 of 2002 on Radioactive Waste Treatment.

 

Timeline

Pursuant to Article 29 (1) of the Nuclear License Regulation, upon submission of the required documents, the Chairperson of BAPETEN will have 10 working days to issue a declaration on the completeness of the required documents.

Pursuant to Articles 29 (3) and (4) of the Nuclear License Regulation, an administrative and technical assessment will then commence, lasting at most 3 months, and will be followed by an issuance of an Exemption Statement if the administrative and technical requirements are met (Article 29 (8)).

 

License Transfer

Pursuant to Article 31 (1) of the Nuclear License Regulation, licenses can be transferred following an approval by the Chairperson of BAPETEN. The Chairperson of BAPETEN will issue a further regulation on the transfer of licenses.

 

Sanctions and Liability

Administrative sanctions

Pursuant to Article 36 of the Nuclear License Regulation, if subsequent licenses are not applied for in time, license extensions are not obtained as required, or activities are not commenced within the provided periods of time, a warning letter will be issued by the Chairperson of BAPETEN. If the warning letter is not complied with within 6 months (with a possibility of a further extension of 6 months), the licenses can be frozen for a 2 year period, ultimately followed by license revocation.

 

Criminal Sanctions

Pursuant to Article 41 of the Nuclear Law, Parties who erect, operate, or decommission a nuclear reactor without the required license, can face imprisonment of 15 years and fines of up to IDR 1 billion.

Nuclear reactor operators who operate a reactor without a license, according to Article 42 of the Nuclear Law can face imprisonment of 2 years and/or a fine of IDR 50 million.

 

Nuclear Accidents

Pursuant to Article 28 of the Nuclear Law, should a nuclear accident occur within the nuclear facility and cause injury to a third party, the owner of the nuclear reactor is liable for any damage caused by the nuclear accident.

Articles 29 through Article 32 of the Nuclear Law stipulate the grounds that have the potential to relieve the owner of a nuclear reactor from such responsibility to a third party.

Pursuant to Article 1 of Government Regulation No. 46 of 2009 on Limits of Liability for Nuclear Damage, the maximum liability of an owner of a nuclear installation is IDR 4 trillion.

 

Conclusion

Feasibility studies to erect a nuclear reactor in Indonesia have been carried out for a number of years, with areas such as Bangka Belitung, Balong Ujung Lemahabang of Jepara in Central Java, and Kalimantan (Borneo) being targeted as potential nuclear power plant sites. However, as of today, none of the plans have come to fruition, assumingly due to the level of scrutiny that such a project has to undergo.

Despite Indonesia having substantial untapped natural resource potential, including geothermal energy (of which Indonesia holds 40% of the world’s reserves), which is promoted by some as a safer alternative energy source than nuclear power, the 2005-2025 development plans include the erection of a nuclear power plant as part of the official national development plan.

If the development plans were to proceed, it is likely that Indonesia’s nuclear reactor projects would be bid on by parties from countries that have developed a substantial level of expertise in utilizing nuclear technology such as Canada, China, France, Japan, Russia, South Korea, and the United States. With the construction, operation, and decommissioning of reactors involving the IAEA.

It is expected that further regulations governing nuclear power will be issued in the future, further expanding the role of BAPETEN.

 

......

Subscribe to read more legal analysis.

Hukumonline Pro Intelligence

Platform AI hukum terpercaya sebagai solusi komprehensif riset Anda

professionalprofessionalProfessional Solutions
professionalprofessionalUniversity Solutions
*Syarat dan ketentuan berlaku

Overview

As of 2011 the International Atomic Energy Agency (IAEA) records show that there are 436 Nuclear Power Plants located in 30 countries, and it is expected that a further 15 to 30 nuclear power plants will be constructed before 2030.

IAEA, as the international organization that is in charge of the supervision on the use of nuclear technology for non-proliferation purposes, has revealed that there are around 60 developing nations that have expressed their desire to use nuclear technology for energy generation purposes.

Indonesia is one of the countries that has expressed its intention to the IAEA, due to constraints in meeting the rising domestic demand for energy. In fact, power shortages have been a regular occurrence in the eastern part of Indonesia, especially on the island of Kalimantan (Borneo).

Indonesia has been preparing itself for the utilization of nuclear energy for a substantial amount of time, beginning with Law No. 31 of 1964 on General Provisions of Atomic Power, as later amended by Law No. 10 of 1997 on Nuclear Energy (“Nuclear Law”). However, until today, the development of nuclear power has not been realized, with the only developments being public discourse and the establishment of preparatory committees for nuclear power plants.

At present only nuclear research facilities exist in Indonesia, where the National Nuclear Agency (Badan Tenaga Nuklir / BATAN) is the leading national research agency on nuclear technology. BATAN has been in existence since 1985, having been established by Presidential Decree No. 82 of 1985 on the National Nuclear Agency. And has been followed by the establishment of the Nuclear Supervision Agency (Badan Pengawas Tenaga Nuklir / BAPETEN) by Presidential Decree No. 76 of 1998 on Nuclear Power Supervision Agency (“BAPETEN Decree”), which in essence functions to formulate national policy for supervising the use of nuclear technology.

This edition of the Indonesian Law Digest will highlight the key features of the legislative framework governing the construction and operation of a nuclear power plant and provide an analysis of the relevant provisions.

 

Purpose

Energy

Dispersed through the regions of Indonesia, energy supplied to consumers by the State Electricity Company (Perusahaan Listrik / PLN) derives from hydro power plants, geothermal power plants, and steam power plant that are fueled by fossil fuels, the price of which has seen substantial appreciation over the recent past.

In producing electricity, different power plant types have different abilities to increase or decrease the electricity output to fulfill the base load demand for energy. Although green alternative renewable energy sources such as wind power plants and solar power plants appear to be favored by the international community, they are unfortunately unable to provide an electricity supply of sufficient stability to cover the base load demand.

A number of countries derive a substantial portion of their electrical generation capacity from nuclear power plants, for instance: Lithuania at 76%, France at 75%, Slovakia at 53%, South Korea at 35%, Japan at 23%, and the United States at 20%.

Indonesia on the other hand, pursuant to Article 2 (6) of Presidential Decree No. 5 of 2006 on National Energy Policy, has stipulated that nuclear power, along with other new and renewable energy sources, has to supply at least 5% of the national energy needs. This policy was further supported by the issuance of Law No. 17 of 2007 on National Long Term Development for 2005-2025.

 

Nuclear Power Plants

As stipulated in Article 2 of the Government Regulation No. 43 of 2006 on Nuclear Reactor Licenses (“Nuclear License Regulation”), the development stages of nuclear power plants and reactors consist of three phases, respectively: erection of the nuclear reactor, operation of the reactor, and decommissioning.

The purpose of this ILD is to provide an overview of the legal framework involved in erecting a nuclear power plant through to the decommissioning phase.

 

Applicability

Pursuant to Article 13 (3) of the Nuclear Law in conjunction with Article 5 (3) of the Nuclear License Regulation, state owned enterprises, cooperatives, or private entities may erect, operate, and decommission nuclear reactors.

 

Foreign Ownership

As stated in Business Classification field (KBLI) number 35101 of Presidential Regulation No. 36 of 2010 on the List of Business Fields Closed to Investment and Business Fields Conditionally Open to Investment (“Negative Investment List”), foreign investors can own up to 95% of a nuclear power plant in Indonesia.

 

Licenses

Pursuant to Article 3 (d) of the BAPETEN Decree in conjunction with Article 6 of the Nuclear License Regulation, licenses for the use of nuclear technology are issued by BAPETEN. However, in relation to erecting a nuclear reactor, pursuant to Article 5 (4) of the Nuclear License Regulation, an applicant first has to secure a determination from the minister in charge of national energy security, whereby the minister has to consult with the House of Representative (Dewan Perwakilan Rakyat / DPR) before rendering its determination.

As set out in Article 6 (2) of the Nuclear License Regulation, an applicant has to secure 5 types of licenses, which are:

a.

Site License;

b.

Construction License;

c.

Commissioning License;

d.

Operating License; and

e.

Decommissioning License.

 

These licenses will be issued on a step-by-step basis by the Chairperson of BAPETEN, with the owner of the nuclear reactor having to secure all 5 licenses, pursuant to the elucidation of the Nuclear License Regulation preamble.

 

Administrative and Technical Requirements

Pursuant to Article 7 of the Nuclear License Regulation, to obtain the required licenses, the applicant has to fulfill the administrative and technical requirements. The administrative requirements include the formation of the legal entity and the compliance with the relevant regulations on legal entities and investment.

The technical requirements include such matters as: the quality assurance program, which consists of a safety system, grading system, documentation, management responsibility; and resource management, which consists of the implementation process, as well as the measurement, assessment and repair of the planned nuclear reactor.

Pursuant to Article 7 (5), the Chairperson of BAPETEN will issue a further regulation on the quality assurance program.

 

Site License

Pursuant to Article 9 of the Nuclear License Regulation, a site license applicant has to submit to the Chairperson of BAPETEN documents consisting of:

a.

The site evaluation report,

b.

Primary data on the planned nuclear reactor,

c.

List of information of the nuclear facility’s preliminary design, and

d.

Documentation on the quality assurance program.

 

Timeline

Pursuant to Article 10 (1) of the Nuclear License Regulation, upon submission of the documents required for a site license, the Chairperson of BAPETEN will have 1 month to issue a declaration on the completeness of the required documents.

Pursuant to Articles 10 (3) and (4) of the Nuclear License Regulation, an administrative and technical assessment will then commence, lasting at most 1 year, and will be followed by an issuance of a site license if the administrative and technical requirements are met (Article 10 (9)).

 

Construction License

A construction license has to be applied for within 4 years of a site license being issued (Article 12 (1) of the Nuclear License Regulation). The application requires the submission of the administrative documents listed in Article 7 (2) as well as the following:

a.

Preliminary safety analysis report,

b.

Detailed design of the nuclear reactor,

c.

Probabilistic safety analysis report on the commercial nuclear reactor,

d.

Construction program,

e.

List of information on the design,

f.

Preliminary Nuclear Safety System, describing the physical protection plan of the facility,

g.

Construction quality assurance program,

h.

An environmental feasibility decision from the appointed institution, and

i.

Evidence of financial capability, to ensure the implementation of construction.

 

Timeline

Pursuant to Article 13 (1) of the Nuclear License Regulation, upon submission of the documents required for a construction license, the Chairperson of BAPETEN will have 1 month to issue a declaration on the completeness of the required documents.

Pursuant to Articles 13 (3) and (4) of the Nuclear License Regulation, an administrative and technical assessment will then commence, lasting at most 2 years, and will be followed by an issuance of a construction license if the administrative and technical requirements are met (Article 13 (8)).

A construction license can be issued for at most 5 years (Article 14 (1) of the Nuclear License Regulation).

 

Commissioning License

Pursuant to Article 15 (1) of the Nuclear License Regulation, it is possible to apply for a commissioning license to the Chairperson of BAPETEN in the event that: the applicant has completed the construction phase; secured a license to utilize nuclear substances; and secured a reactor operator that holds a working license (such licenses being governed by Government Regulation No. 29 of 2008 on Licenses for the Use of Ionizing Radiation Sources and Nuclear Materials).

Pursuant to Article 15 (2), in addition to the administrative documents required by Article 7 (2), the following technical documents have to be submitted:

a.

Commissioning program,

b.

 Report on the construction process, including function test results on the structure, systems, and components of the nuclear reactor,

c.

Technical drawings of the nuclear reactor,

d.

Safeguard system and the Nuclear Safety System,

e.

Nuclear preparedness program,

f.

Commissioning quality assurance program,

g.

Environmental management and environmental monitoring reports,

h.

Evidence of financial capability, to ensure the accountability for any nuclear damage, and

i.

Evidence of financial capability, to guarantee decommissioning.

 

Timeline

Pursuant to Article 16 (1) of the Nuclear License Regulation, upon submission of the documents required for a commissioning license, the Chairperson of BAPETEN will have 1 month to issue a declaration on the completeness of the required documents.

Pursuant to Articles 16 (3) and (4) of the Nuclear License Regulation, an administrative and technical assessment will then commence, lasting at most 1 year, and will be followed by an issuance of a commissioning license if the administrative and technical requirements are met (Article 16 (8)).

A commissioning license can be issued for at most 2 years (Article 17 (1) of the Nuclear License Regulation), with implementation having to commence within 6 months of the license being issued.

 

Operating License

Pursuant to Article 18 (1) of the Nuclear License Regulation, it is possible to apply for an operating license to the Chairperson of BAPETEN in the event that: the applicant has completed the commissioning phase; secured a license to utilize nuclear substances; and secured a reactor operator that holds a working license (such licenses being governed by Government Regulation No. 29 of 2008 on Licenses for the Use of Ionizing Radiation Sources and Nuclear Materials).

Pursuant to Article 18 (2), in addition to the administrative documents required by Article 7 (2), the following technical documents have to be submitted:

a.

A final safety analysis report that includes the commissioning results, limitations and conditions of the nuclear facility’s operation, and the decommissioning program,

b.

Nuclear substance safeguard facility appendices,

c.

Report on the implementation of environmental management and environmental monitoring during commissioning,

d.

Operational quality assurance program,

e.

Evidence of financial capability to operate the nuclear facility.

 

Timeline

Pursuant to Article 19 (1) of the Nuclear License Regulation, upon submission of the documents required for an operating license, the Chairperson of BAPETEN will have 1 month to issue a declaration on the completeness of the required documents.

Pursuant to Articles 19 (3) and (4) of the Nuclear License Regulation, an administrative and technical assessment will then commence, lasting at most 2 years, and will be followed by an issuance of an operating license if the administrative and technical requirements are met (Article 19 (8)).

An operating license will be issued for at most 40 years (Article 20 (1) of the Nuclear License Regulation).

 

Operating License Extension

Since there are nuclear reactors designed to operate for more than 40 years, pursuant to Article 20 (2), at least 5 years prior to the expiry of the operating license, it is possible to request a license extension, which requires the submission of:

a.

Final safety analysis report,

b.

Operational activity report, and

c.

Aging research report.

 

Pursuant to Articles 20 (5) and (6), should the assessment by the Chairperson of BAPETEN find that the technical requirements have been fulfilled, the operating license will be extended for a further 20 years.

 

Decommissioning License

Nuclear reactor decommissioning is one of the obligations that a nuclear reactor owner is obliged to fulfill at the end of the lifecycle of a nuclear reactor. Pursuant to Article 24 (3) of the Nuclear License Regulation, at least 3 years prior to the expiry of the operating license an application for a decommissioning license has to be submitted to the Chairperson of BAPETEN.

Pursuant to Article 24 (2) of the Nuclear License Regulation, in addition to the administrative documents required by Article 7 (2), the following technical documents have to be submitted:

a.

Decommission program, and

b.

Decommission quality assurance program.

 

Timeline

Pursuant to Article 25 (1) of the Nuclear License Regulation, upon submission of the documents required for a decommissioning license, the Chairperson of BAPETEN will have 1 month to issue a declaration on the completeness of the required documents.

Pursuant to Articles 25 (3) and (4) of the Nuclear License Regulation, an administrative and technical assessment will then commence, lasting at most 1 year, and will be followed by an issuance of a decommissioning license if the administrative and technical requirements are met (Article 25 (8)).

A decommissioning license will remain valid until the issuance of the Exemption Statement by the Chairperson of BAPETEN (Article 26 of the Nuclear License Regulation).

 

Exemption Statement

To be relieved of the decommissioning obligation, pursuant to Article 28 (1) of the Nuclear License Regulation, a nuclear reactor owner has to secure an Exemption Statement from the Chairperson of BAPETEN. To obtain an Exemption Statement the owner has to submit:

a.

Report on the decommissioning of the nuclear reactor,

b.

Report on the treatment of the radioactive waste, and

c.

Report on environmental monitoring, including test results of radiation exposure and radioactive contamination inside and outside of the reactor site.

 

In treating radioactive waste it is necessary to comply with the provisions of Government Regulation No. 27 of 2002 on Radioactive Waste Treatment.

 

Timeline

Pursuant to Article 29 (1) of the Nuclear License Regulation, upon submission of the required documents, the Chairperson of BAPETEN will have 10 working days to issue a declaration on the completeness of the required documents.

Pursuant to Articles 29 (3) and (4) of the Nuclear License Regulation, an administrative and technical assessment will then commence, lasting at most 3 months, and will be followed by an issuance of an Exemption Statement if the administrative and technical requirements are met (Article 29 (8)).

 

License Transfer

Pursuant to Article 31 (1) of the Nuclear License Regulation, licenses can be transferred following an approval by the Chairperson of BAPETEN. The Chairperson of BAPETEN will issue a further regulation on the transfer of licenses.

 

Sanctions and Liability

Administrative sanctions

Pursuant to Article 36 of the Nuclear License Regulation, if subsequent licenses are not applied for in time, license extensions are not obtained as required, or activities are not commenced within the provided periods of time, a warning letter will be issued by the Chairperson of BAPETEN. If the warning letter is not complied with within 6 months (with a possibility of a further extension of 6 months), the licenses can be frozen for a 2 year period, ultimately followed by license revocation.

 

Criminal Sanctions

Pursuant to Article 41 of the Nuclear Law, Parties who erect, operate, or decommission a nuclear reactor without the required license, can face imprisonment of 15 years and fines of up to IDR 1 billion.

Nuclear reactor operators who operate a reactor without a license, according to Article 42 of the Nuclear Law can face imprisonment of 2 years and/or a fine of IDR 50 million.

 

Nuclear Accidents

Pursuant to Article 28 of the Nuclear Law, should a nuclear accident occur within the nuclear facility and cause injury to a third party, the owner of the nuclear reactor is liable for any damage caused by the nuclear accident.

Articles 29 through Article 32 of the Nuclear Law stipulate the grounds that have the potential to relieve the owner of a nuclear reactor from such responsibility to a third party.

Pursuant to Article 1 of Government Regulation No. 46 of 2009 on Limits of Liability for Nuclear Damage, the maximum liability of an owner of a nuclear installation is IDR 4 trillion.

 

Conclusion

Feasibility studies to erect a nuclear reactor in Indonesia have been carried out for a number of years, with areas such as Bangka Belitung, Balong Ujung Lemahabang of Jepara in Central Java, and Kalimantan (Borneo) being targeted as potential nuclear power plant sites. However, as of today, none of the plans have come to fruition, assumingly due to the level of scrutiny that such a project has to undergo.

Despite Indonesia having substantial untapped natural resource potential, including geothermal energy (of which Indonesia holds 40% of the world’s reserves), which is promoted by some as a safer alternative energy source than nuclear power, the 2005-2025 development plans include the erection of a nuclear power plant as part of the official national development plan.

If the development plans were to proceed, it is likely that Indonesia’s nuclear reactor projects would be bid on by parties from countries that have developed a substantial level of expertise in utilizing nuclear technology such as Canada, China, France, Japan, Russia, South Korea, and the United States. With the construction, operation, and decommissioning of reactors involving the IAEA.

It is expected that further regulations governing nuclear power will be issued in the future, further expanding the role of BAPETEN.

 

......

Subscribe to read more legal analysis.

Hukumonline Pro Intelligence

Platform AI hukum terpercaya sebagai solusi komprehensif riset Anda

professionalprofessionalProfessional Solutions
professionalprofessionalUniversity Solutions
*Syarat dan ketentuan berlaku
2026 Hak Cipta Milik Hukumonline.com
Cookies Info