Governor of Jakarta Regulation Aims to Optimize the Installation of Underground Utility Networks

Overview

Governor of Jakarta Regulation No. 128 of 2010 on the Installation of Utility Networks in Strategic Locations (‘Regulation’) has come into force on 8 July 2010, repealing its predecessors, Governor Decision No. 439 of 1991 and Governor Decision No. 615/1999, pursuant to Article 19.

The Regulation contains provisions regarding the installation of utility networks in the greater Jakarta area (Special Capital Territory (DKI) of Jakarta), in areas such as national roads and other locations that are designated by the provincial government, pursuant to Article 6.

This edition of the Indonesian Law Digest will highlight key features of the Regulation and provide analysis of the Regulation’s provisions.

 

Purpose

The Regulation aims to optimize the placement of utility networks, allowing the optimal use of space. And aims to have a more organized utilization of urban spaces.

As such, the Regulation can be seen as an attempt by the Governor to bring order to the layout and installation of utility networks within the capital. The focus on ‘strategic locations’ suggests that the regulation aims to ensure that utility network installation projects taking place in the vicinity of roads are more orderly and less disruptive (with Article 6 (3), for example disallowing open trench installation, and instead requiring horizontal directional drilling or micro tunnelling).

In order to assist with this goal, among other things, the Regulation aims to simplify the licensing procedures for the installation of utility networks in strategic locations.

 

Definitions and Applicability

Strategic locations are defined by Articles 6 (1) and (2) as those stipulated by the Public Works Agency (in coordination with the Regional Works Unit (SKPD/UKPD)), which are prioritized for utility network placement. Such locations are those that are parallel to, and intersect, national roads, highways, artery roads, collector roads, green zones, pedestrian and certain other roads, as stipulated by the Public Works Agency.

Utility Networks are defined, by Article 1 (12), as network systems consisting of pipes and/or cable. Making the Regulation applicable to a broad range of underground utility installation works that are carried out in Jakarta pursuant to Article 5 (1), which requires a licence to be obtained for any such works.

The Regulation, pursuant to Article 1 (16), applies to ‘institutions,’ who are defined as the owners of the utility networks. And to ‘service providers,’ (contractors) who, according to Article 1 (17), are defined as the persons or businesses engaged in the provision of construction services.

 

Planning

The Regulation, pursuant to Article 3 (1) aims to integrate the planning and underground installation of utility networks, and, in order to achieve this, under Article 2 (1), creates a planning obligation for the institutions. The planning obligation requires institutions to submit an annual plan that details the location, capacity requirements, dimensions, cost estimates, and installation methods of the needed utility networks to the Head of the Public Works Agency no later than the September of the preceding year.

These annual reports then contribute to the integrated planning, which will be carried out by the Governor. With the ultimate installation of the utility network being in accordance with the general principles enumerated in Article 4 (3), such as, being in line with the regional development goals, encouraging economic growth, and improving the quality of service, among others.

 

Licensing

Article 5 (1) requires a licence to be obtained for any underground utility network installation activities to take place.

The application procedure is set out in Article 5 (2), and requires an application to be submitted to the Public Works Agency, containing:

a)

blueprints of the utility network placement plan, at a scale of 1:5000 for placement, and cross sectional drawings at a scale of 1:100 for pipe of diameter above 600mm;

b)

blueprints of the utility network placement plan at a scale of 1:1000 for data networks;

c)

limit or notation on the length, diameter and number of channels;

d)

layout diagrams, including diagrams of the location of the road crossing;

e)

installation work schedule; and

f)

a copy of the terms of references (TOR) for replacement works and/or the existing utility network placing.

 

Once submitted, the application is subject to the review procedures set out in Article 7. Whereby the Public Works Agency will:

-

review the administrative completeness of the documents;

-

conduct a joint hearing to review the application and the annual program;

-

conduct a site visit (together with the institution and the SKPD/UKPD) to determine such matters as traffic regulation;

-

set the levy payable by the institution for the use of the underground location or the existing network facilities (with further regulation due to set out the amounts and payment procedures pursuant to Article 14); and

-

set the security deposit for the repairs that will be necessary following the excavation.

 

Once issued, the license is valid for a specified period, as indicated in the license pursuant to Article 8 (1). With a possibility of extension, under Articles 8 (1) through (3), in the event that the works have not been completed. In order to obtain such an extension, an application has to contain the reasons for the works not being completed in the allotted time. With only a single extension being allowed.

Additionally, under Article 9, if the implementation of the utility network installation has not commenced within 30 days of the licence being issued, the license can be revoked.

 

Installation

Contractors are obliged to conduct certain pre-installation activities, as enumerated by Article 10, such as:

a)

report to the local city/district administrative office at least 3 days prior to excavation;

b)

conduct a field review;

c)

install safety signs; and

d)

prepare the necessary tools, materials, and manpower prior to commencing excavation.

 

The excavation itself has to comply with the technical requirements set out in Article 11. With a notable requirement being that any roads that are dug up, have to be repaired within 24 hours. And the contractor being liable for any damage caused by the work, pursuant to Article 11 (5). Also of note is Article 6 (3), which disallows open trench installation, instead requiring horizontal directional drilling or micro tunnelling / pipe jacking.

Post installation repair works are specifically addressed by Article 12, which states that the work can either be conducted by the local government, using the security deposit paid by the institution under Article 7 (e) or by the institution itself, in which event the security deposit is refunded pursuant to Article 12 (3).

 

Other Considerations

Relocation

In the event that an underground utility network has to be relocated due to works being carried out by the local government, Article 13 (1) states that the Governor can order the affected institution/contractor to carry out any such relocation. The Governor, pursuant to Article 13 (2), has to give at least one year’s notice of the required relocation to the affected institution/contractor.

 

Guidance and Supervision

Various guidance on utility network installation will be provided by the Public Works Agency to institutions and contractors pursuant to Article 15. With supervision being conducted pursuant to Article 16, which states that a technical supervisor, as defined in Article 1 (19), will oversee the excavation as well as the subsequent repair works.

Furthermore, under Article 17, the Head of the Public Works Agency will have control over the implementation of utility network installation, and will hold coordination meetings, potentially with the SKPD/UKPD, every 3 months, or as required. The results of any such meetings will then be reported to the Governor.

 

Sanctions

Article 18 sets out the sanctions regime imposed by the Regulation in the event that violations are discovered during the Article 16 and 17 supervision and control reviews. Such administrative sanctions can consist of written notices and orders to cease the utility network installation activities.

Two written notices will be given pursuant to Article 18 (2), the first having a 168 hour (7 day) grace period, and the second having a 72 hour (3 day) grace period. After which point, if the notice letters are not complied with, a warning letter may be given with a 72 hour (3 day) grace period.

In the event that the written notices and the warning letter are not complied with, the installation works will become subject to a cessation of activities order under Article 18 (3). Following such an order, the contractor conducting the works can be prohibited from engaging in any further excavation, installation, or repair of utility networks in DKI Jakarta for a period of one year under Article 18 (5).

 

Conclusion

The Regulation goes some ways to streamlining the permit process for conducting underground utility network installation works in DKI Jakarta, and, as such should be commended both for setting out the procedures as well as the broader goals of coordinating such installation works. At the same time, however, the Regulation seems to gloss over certain issues, such as the exact nature of the integrated planning discussed in Article 3, and leaves other issues to be resolved by future regulations, such as the amounts and payment mechanism of Article 7 (d) levies under Article 14. Finally, the potentially costly obligation to relocate utility networks under Article 13 could certainly benefit from a mere precise definition of the situations when such relocations can be requested by local government, and whether any compensation would be available. Similarly, the Article 7 (e) repair security deposit calculation and payment procedure would ideally be made more transparent, either within the regulation, or by means of further regulation, as is the intent to do with levies under Article 14

The Regulation appears to be at least partially motivated by concerns over traffic disturbances caused by excavation works next to public roads, as can be seen from a number of provisions, such as Articles 7 (c) (5) and 11 (2). In light of this, and Jakarta’s constant traffic problems, any efforts to reduce traffic disruptions should be commended. Nonetheless, the one-size-fits-all 24 hour restriction appears to be indicative of knee-jerk attempts to patch up traffic problems, rather than taking a closer look at the works being carried out, and, ultimately, at the wider issuer of underdeveloped infrastructure.

 

......

Subscribe to read more legal analysis.

Hukumonline Pro Intelligence

Platform AI hukum terpercaya sebagai solusi komprehensif riset Anda

professionalprofessionalProfessional Solutions
professionalprofessionalUniversity Solutions
*Syarat dan ketentuan berlaku

Overview

Governor of Jakarta Regulation No. 128 of 2010 on the Installation of Utility Networks in Strategic Locations (‘Regulation’) has come into force on 8 July 2010, repealing its predecessors, Governor Decision No. 439 of 1991 and Governor Decision No. 615/1999, pursuant to Article 19.

The Regulation contains provisions regarding the installation of utility networks in the greater Jakarta area (Special Capital Territory (DKI) of Jakarta), in areas such as national roads and other locations that are designated by the provincial government, pursuant to Article 6.

This edition of the Indonesian Law Digest will highlight key features of the Regulation and provide analysis of the Regulation’s provisions.

 

Purpose

The Regulation aims to optimize the placement of utility networks, allowing the optimal use of space. And aims to have a more organized utilization of urban spaces.

As such, the Regulation can be seen as an attempt by the Governor to bring order to the layout and installation of utility networks within the capital. The focus on ‘strategic locations’ suggests that the regulation aims to ensure that utility network installation projects taking place in the vicinity of roads are more orderly and less disruptive (with Article 6 (3), for example disallowing open trench installation, and instead requiring horizontal directional drilling or micro tunnelling).

In order to assist with this goal, among other things, the Regulation aims to simplify the licensing procedures for the installation of utility networks in strategic locations.

 

Definitions and Applicability

Strategic locations are defined by Articles 6 (1) and (2) as those stipulated by the Public Works Agency (in coordination with the Regional Works Unit (SKPD/UKPD)), which are prioritized for utility network placement. Such locations are those that are parallel to, and intersect, national roads, highways, artery roads, collector roads, green zones, pedestrian and certain other roads, as stipulated by the Public Works Agency.

Utility Networks are defined, by Article 1 (12), as network systems consisting of pipes and/or cable. Making the Regulation applicable to a broad range of underground utility installation works that are carried out in Jakarta pursuant to Article 5 (1), which requires a licence to be obtained for any such works.

The Regulation, pursuant to Article 1 (16), applies to ‘institutions,’ who are defined as the owners of the utility networks. And to ‘service providers,’ (contractors) who, according to Article 1 (17), are defined as the persons or businesses engaged in the provision of construction services.

 

Planning

The Regulation, pursuant to Article 3 (1) aims to integrate the planning and underground installation of utility networks, and, in order to achieve this, under Article 2 (1), creates a planning obligation for the institutions. The planning obligation requires institutions to submit an annual plan that details the location, capacity requirements, dimensions, cost estimates, and installation methods of the needed utility networks to the Head of the Public Works Agency no later than the September of the preceding year.

These annual reports then contribute to the integrated planning, which will be carried out by the Governor. With the ultimate installation of the utility network being in accordance with the general principles enumerated in Article 4 (3), such as, being in line with the regional development goals, encouraging economic growth, and improving the quality of service, among others.

 

Licensing

Article 5 (1) requires a licence to be obtained for any underground utility network installation activities to take place.

The application procedure is set out in Article 5 (2), and requires an application to be submitted to the Public Works Agency, containing:

a)

blueprints of the utility network placement plan, at a scale of 1:5000 for placement, and cross sectional drawings at a scale of 1:100 for pipe of diameter above 600mm;

b)

blueprints of the utility network placement plan at a scale of 1:1000 for data networks;

c)

limit or notation on the length, diameter and number of channels;

d)

layout diagrams, including diagrams of the location of the road crossing;

e)

installation work schedule; and

f)

a copy of the terms of references (TOR) for replacement works and/or the existing utility network placing.

 

Once submitted, the application is subject to the review procedures set out in Article 7. Whereby the Public Works Agency will:

-

review the administrative completeness of the documents;

-

conduct a joint hearing to review the application and the annual program;

-

conduct a site visit (together with the institution and the SKPD/UKPD) to determine such matters as traffic regulation;

-

set the levy payable by the institution for the use of the underground location or the existing network facilities (with further regulation due to set out the amounts and payment procedures pursuant to Article 14); and

-

set the security deposit for the repairs that will be necessary following the excavation.

 

Once issued, the license is valid for a specified period, as indicated in the license pursuant to Article 8 (1). With a possibility of extension, under Articles 8 (1) through (3), in the event that the works have not been completed. In order to obtain such an extension, an application has to contain the reasons for the works not being completed in the allotted time. With only a single extension being allowed.

Additionally, under Article 9, if the implementation of the utility network installation has not commenced within 30 days of the licence being issued, the license can be revoked.

 

Installation

Contractors are obliged to conduct certain pre-installation activities, as enumerated by Article 10, such as:

a)

report to the local city/district administrative office at least 3 days prior to excavation;

b)

conduct a field review;

c)

install safety signs; and

d)

prepare the necessary tools, materials, and manpower prior to commencing excavation.

 

The excavation itself has to comply with the technical requirements set out in Article 11. With a notable requirement being that any roads that are dug up, have to be repaired within 24 hours. And the contractor being liable for any damage caused by the work, pursuant to Article 11 (5). Also of note is Article 6 (3), which disallows open trench installation, instead requiring horizontal directional drilling or micro tunnelling / pipe jacking.

Post installation repair works are specifically addressed by Article 12, which states that the work can either be conducted by the local government, using the security deposit paid by the institution under Article 7 (e) or by the institution itself, in which event the security deposit is refunded pursuant to Article 12 (3).

 

Other Considerations

Relocation

In the event that an underground utility network has to be relocated due to works being carried out by the local government, Article 13 (1) states that the Governor can order the affected institution/contractor to carry out any such relocation. The Governor, pursuant to Article 13 (2), has to give at least one year’s notice of the required relocation to the affected institution/contractor.

 

Guidance and Supervision

Various guidance on utility network installation will be provided by the Public Works Agency to institutions and contractors pursuant to Article 15. With supervision being conducted pursuant to Article 16, which states that a technical supervisor, as defined in Article 1 (19), will oversee the excavation as well as the subsequent repair works.

Furthermore, under Article 17, the Head of the Public Works Agency will have control over the implementation of utility network installation, and will hold coordination meetings, potentially with the SKPD/UKPD, every 3 months, or as required. The results of any such meetings will then be reported to the Governor.

 

Sanctions

Article 18 sets out the sanctions regime imposed by the Regulation in the event that violations are discovered during the Article 16 and 17 supervision and control reviews. Such administrative sanctions can consist of written notices and orders to cease the utility network installation activities.

Two written notices will be given pursuant to Article 18 (2), the first having a 168 hour (7 day) grace period, and the second having a 72 hour (3 day) grace period. After which point, if the notice letters are not complied with, a warning letter may be given with a 72 hour (3 day) grace period.

In the event that the written notices and the warning letter are not complied with, the installation works will become subject to a cessation of activities order under Article 18 (3). Following such an order, the contractor conducting the works can be prohibited from engaging in any further excavation, installation, or repair of utility networks in DKI Jakarta for a period of one year under Article 18 (5).

 

Conclusion

The Regulation goes some ways to streamlining the permit process for conducting underground utility network installation works in DKI Jakarta, and, as such should be commended both for setting out the procedures as well as the broader goals of coordinating such installation works. At the same time, however, the Regulation seems to gloss over certain issues, such as the exact nature of the integrated planning discussed in Article 3, and leaves other issues to be resolved by future regulations, such as the amounts and payment mechanism of Article 7 (d) levies under Article 14. Finally, the potentially costly obligation to relocate utility networks under Article 13 could certainly benefit from a mere precise definition of the situations when such relocations can be requested by local government, and whether any compensation would be available. Similarly, the Article 7 (e) repair security deposit calculation and payment procedure would ideally be made more transparent, either within the regulation, or by means of further regulation, as is the intent to do with levies under Article 14

The Regulation appears to be at least partially motivated by concerns over traffic disturbances caused by excavation works next to public roads, as can be seen from a number of provisions, such as Articles 7 (c) (5) and 11 (2). In light of this, and Jakarta’s constant traffic problems, any efforts to reduce traffic disruptions should be commended. Nonetheless, the one-size-fits-all 24 hour restriction appears to be indicative of knee-jerk attempts to patch up traffic problems, rather than taking a closer look at the works being carried out, and, ultimately, at the wider issuer of underdeveloped infrastructure.

 

......

Subscribe to read more legal analysis.

Hukumonline Pro Intelligence

Platform AI hukum terpercaya sebagai solusi komprehensif riset Anda

professionalprofessionalProfessional Solutions
professionalprofessionalUniversity Solutions
*Syarat dan ketentuan berlaku
2026 Hak Cipta Milik Hukumonline.com
Cookies Info