Guidelines for Building and Using Joint Telecommunication Towers

This is the Regulation that telecommunications providers and tower builders have been waiting on for some time and is the culmination of the public consultation process (see ILB No. 380 2/8/2006). The Regulation No. 02/PER/M.KOMINFO/3/2008, was signed by the Minister of Communications and Information on 17 March 2008 and the provisions came into immediate force.

 

The main provisions of the Regulation are as follow:

  • For the purposes of efficiency and effectiveness in the use of available space all towers are to be used jointly by all providers. The Regulation relies on the provisions of the Anti-Monopoly Law to ensure that telecommunication tower developers do not engage in monopolistic practices in the use of the towers built;

  • Telecommunication towers may be built by telecommunication providers, tower providers, and/or tower contractors;

  • In order to prevent the indiscriminate building of telecommunication towers wherever a builder sees fit the Regulation explicitly requires that all towers are licensed;

  • The local governments in their respective jurisdictions are to be responsible for enacting legislation regarding the placement of towers with reference to any other prevailing laws and regulations in this sector;

  • Construction services as they relate to the construction of towers is a sector that is closed to foreign capital investment;

  • Tower suppliers, managers, or contractors must be Indonesian owned inclusive of all capital and shares;

  • Towers are required to satisfy applicable quality standards and include requisite safety features such as groundings, lightening rods, aviation obstruction lights, and aviation obstruction markers, among others;

  • The legal status relating to the ownership of the tower must be clear;

  • Irrespective of tower ownership, all telecommunications providers are to have non-discriminatory access to the relevant towers in accordance with the technical capabilities of the tower;

  • All agreements relating to the use of the relevant towers are to be in writing and registered with the Directorate General of Post and Telecommunications;

  • Not all towers are subject to the provisions contained in the Regulation. The exceptions include towers that are used for the primary network, towers built in areas where there is no telecommunications services, or where the relevant regions make this economically infeasible;

  • There is a 2-year grace period for towers that were licensed prior to the enactment of this Regulation to enter into compliance with the provisions of this Regulation; and

  • The government, central or regional, may enforce administrative sanctions for the breach of these provisions in the form of written warnings, fines, and the cancellation of licenses.

......

Subscribe to read more legal analysis.

Hukumonline Pro Intelligence

Platform AI hukum terpercaya sebagai solusi komprehensif riset Anda

professionalprofessionalProfessional Solutions
professionalprofessionalUniversity Solutions
*Syarat dan ketentuan berlaku

This is the Regulation that telecommunications providers and tower builders have been waiting on for some time and is the culmination of the public consultation process (see ILB No. 380 2/8/2006). The Regulation No. 02/PER/M.KOMINFO/3/2008, was signed by the Minister of Communications and Information on 17 March 2008 and the provisions came into immediate force.

 

The main provisions of the Regulation are as follow:

  • For the purposes of efficiency and effectiveness in the use of available space all towers are to be used jointly by all providers. The Regulation relies on the provisions of the Anti-Monopoly Law to ensure that telecommunication tower developers do not engage in monopolistic practices in the use of the towers built;

  • Telecommunication towers may be built by telecommunication providers, tower providers, and/or tower contractors;

  • In order to prevent the indiscriminate building of telecommunication towers wherever a builder sees fit the Regulation explicitly requires that all towers are licensed;

  • The local governments in their respective jurisdictions are to be responsible for enacting legislation regarding the placement of towers with reference to any other prevailing laws and regulations in this sector;

  • Construction services as they relate to the construction of towers is a sector that is closed to foreign capital investment;

  • Tower suppliers, managers, or contractors must be Indonesian owned inclusive of all capital and shares;

  • Towers are required to satisfy applicable quality standards and include requisite safety features such as groundings, lightening rods, aviation obstruction lights, and aviation obstruction markers, among others;

  • The legal status relating to the ownership of the tower must be clear;

  • Irrespective of tower ownership, all telecommunications providers are to have non-discriminatory access to the relevant towers in accordance with the technical capabilities of the tower;

  • All agreements relating to the use of the relevant towers are to be in writing and registered with the Directorate General of Post and Telecommunications;

  • Not all towers are subject to the provisions contained in the Regulation. The exceptions include towers that are used for the primary network, towers built in areas where there is no telecommunications services, or where the relevant regions make this economically infeasible;

  • There is a 2-year grace period for towers that were licensed prior to the enactment of this Regulation to enter into compliance with the provisions of this Regulation; and

  • The government, central or regional, may enforce administrative sanctions for the breach of these provisions in the form of written warnings, fines, and the cancellation of licenses.

......

Subscribe to read more legal analysis.

Hukumonline Pro Intelligence

Platform AI hukum terpercaya sebagai solusi komprehensif riset Anda

professionalprofessionalProfessional Solutions
professionalprofessionalUniversity Solutions
*Syarat dan ketentuan berlaku
2026 Hak Cipta Milik Hukumonline.com
Cookies Info